TRAFFIC ALERT – Earthwork Activities to Begin 8/14 – 9/4

TRAFFIC ALERT
EARTHWORK ACTIVITIES TO BEGIN AUGUST 14 THROUGH SEPTEMBER 4

Crews will soon begin construction of the retaining walls for the temporary detour bridge. In preparation for this work, earthwork truck deliveries will be using eastbound and westbound E. 11th Street from N. MacArthur Drive to Cabe Road. Flaggers will be in place to monitor traffic control as well as assist trucks entering and leaving the construction site.

Work is anticipated to begin August 14 and last through September 4. Hours will be from 6:00 a.m. to 6:00 p.m. Monday through Friday and on Saturdays as needed.

Expect heavy congestion and delays on northbound N. MacArthur Drive at the E. 11th Street intersection. Also expect impacts to AM/PM commute traffic as well as to Tracy High School.

The City recommends using alternate routes to avoid the construction zone.